City Court Apartments — Fabrication & Erection — fabrication & erection construction project completed by Build & Care Development Ltd. in Mirpur, Dhaka
420 MT Steel Fabricated Erected in 52 Days
Project Overview

What We Delivered

A tight urban plot with no room for prolonged wet works called for a steel-framed solution: fabricate off site, erect fast, and keep the road open for the neighbourhood throughout.

Build & Care handled shop drawings, workshop fabrication of 420 metric tonnes, site erection and the finishing works that followed.

The Challenge

The site had a single narrow access road shared with residents, so deliveries and craneage had to fit into short, scheduled windows.

Our Approach

Steel was delivered in erection sequence to a just-in-time schedule, with lifts planned into agreed daily windows so the road stayed usable.

The Outcome

The frame topped out in 52 days with zero connection rework and no formal complaint from the neighbourhood throughout erection.

Scope of Work

  • Shop drawing development & approval
  • Workshop steel fabrication — 420 MT
  • Sequenced site erection & alignment
  • Cladding, painting & finishing works
  • Dimensional survey & handover

Project Gallery

Click any photo to open the full gallery.

Your Project Deserves the Same Care.

Tell us what you are planning — we will bring the same discipline, documentation and delivery to your site.

Get a Free Quote